PRESS RELEASES
NOVEMBER, 2011
November 28, 2011
PRESS RELEASE
(IMMEDIATE RELEASE)
Due to weather conditions, the Fairfield County
Engineer’s Office is announcing a delay in the closing of
Pickerington Road (CR20).
The area of Pickerington Road that was scheduled to close today has
been postponed until Wednesday, November 30, 2011, and will be closed for
approximately two (2) days. This
closure will be between Basil-Western Road and Busey Road with construction
taking place between house number 8185 Pickerington Road and Busey Road.
November 22, 2011
PRESS RELEASE
(IMMEDIATE RELEASE)
The Fairfield County Engineer’s Office is announcing that
the following road in VIOLET TOWNSHIP will be closed for a culvert repair.
Pickerington Road (CR20) will be closed for approximately two (2)
days beginning Monday, November 28, 2011.
This closure will be between Basil-Western Road and Busey Road with
construction taking place between house number 8185 Pickerington Road and Busey
Road.
November 22, 2011
PRESS RELEASE
(IMMEDIATE RELEASE)
The Fairfield County Engineer’s Office is announcing that
the following roads in GREENFIELD TOWNSHIP are open for traffic.
Election House Road (CR40) and the
Victor Road (TR1662)/Kull Road (TR1661) Intersection are now open to
the traveling public. Election House
Road was closed between Kull Road and Coonpath Road in connection with the
Fairfield County Airport Authority Project.
November 17, 2011
PRESS RELEASE
(IMMEDIATE RELEASE)
The Fairfield County Engineer’s Office is announcing that
Ety Road in the City of Lancaster has
reopened to traffic. This closure
was between Alanwick Drive and Riversedge Drive with construction taking place
between house number 1121 Ety Road and Riversedge Drive.
November 14, 2011
PRESS RELEASE
(IMMEDIATE RELEASE)
The Fairfield County Engineer’s Office is announcing that
Gun Barrel Road (TR 413) in RICHLAND
TOWNSHIP has reopened to traffic.
This closure was between Miller Siding Road and Bope Road.
November 3, 2011
PRESS RELEASE
(IMMEDIATE RELEASE)
Due to the closure of Election House Road and the impact
of a closure to the traveling public on Election Day, the Fairfield County
Engineer’s Office will be postponing the construction on
Ety Road in the City of Lancaster.
Ety Road will now be closed for approximately four (4) days beginning at
7:00 a.m. Monday, November 14, 2011 until approximately 3:30 p.m. Thursday,
November 17, 2011 for bridge repair work on the GRE-17 bridge.
This closure will be between Alanwick Drive and Riversedge Drive with
construction taking place between house number 1121 Et Road and Riversedge
Drive.
November 1, 2011
PRESS RELEASE
(IMMEDIATE RELEASE)
The Fairfield County Engineer’s Office is announcing that
the following road in GREENFIELD TOWNSHIP will be closed for bridge repair work.
Ety Road in the City of Lancaster will be closed for approximately
four (4) days beginning at 7:00 a.m. Monday, November 7, 2011 until
approximately 3:30 p.m. Thursday, November 10, 2011 for bridge repair work on
the GRE-17 bridge. This closure will
be between Alanwick Drive and Riversedge Drive with construction taking place
between house number 1121 Ety Road and Riversedge Drive.